Logical
|
|
|
Experience - Safety EngineeringWe are intending to post a complete set of data from one of the HSE sponsored large scale explosion tests here together with a FREE trial version of the powerful software required to interpret the results (Dynatool from CREA Consultants Ltd.). Also see the free sample software page Free Software We also have a number of
specialists available to help if required. AGIP – Kashagan Design
of explosion proof enclosures Project Manager of this £0.25 million, 3 month project to design explosion-proof enclosures for the process facilities. The sour (H2S) nature of the gas at the Kashagan field has meant that a re-assessment of the layout of the field has been necessary to reduce the operating risk and availability of the planned facilities. One solution was to enclose the process units consisting of pile supported barges, pre assembled units and modules founded on artificial islands. These enclosures must contain gas releases, fires and explosions as well as protecting plant under maintenance from the impact of these events on neighbouring enclosures. The project team designed a number of enclosures to resist overpressures up to 8 bar to a level suitable for Feed. Design and analysis of the enclosures was performed using SACS and ABAQUS. Constructability, transportation and installation issues were also addressed leading to cost estimates for this solution. HSE/BP - Response Spectra BP Author of a philosophy document on the design of structures to resist fires and explosions for use by BP worldwide. Exxon – ASABO
Assessment of three platform complex in Nigeria for explosion response. UKOOA/HSE – FAB
Responsible for editing, authoring and assembling the new Part 1 Guidance
on fire and explosion engineering. References 60 and 61 – see Publications MMS
(US Materials Management Service) – Development of the technical content, web
site and structure of the workshop on fire and blast engineering held in Houston
during June 2002. API - New Recommended Practice on fire and blast engineering. Corresponding member of the committee and author of the basis document Guidance for the protection of offshore structures against fires and explosions’ Reference 57 - see Publications. BCL Bateman Chapman Limited
– International Loss Adjusters
2001
- date Responsible
for the generation of a large databases and negotiation software for use in
assessing a number of large insurance claims. Steve has also been involved in
the framing of witness questions for depositions to Court and the preparation of
presentation material for negotiation purposes. Relevant
Experience
– all
completed insurance claims were settled out of Court As part
of Logical Software's commercial and legal support activities, Steve Walker has
been responsible for the examination of the Safety, Management and Operational
issues resulting in loss and subsequent insurance claims. Sinking
of the P36 semi-submersible production platform offshore Brazil. 2001
– 2006 For this dispute between the Operating and Construction Insurers, Steve acted for the Design Contractors and construction insurers. It was necessary to examine all the design documentation in order to assess Safety and Operational issues along with documentation of events leading up to the loss. The
activities undertaken during the four years of the project included:-
Steve attended and presented at the dispute
resolution meeting for this claim. Dispute
relating to coating failure on the Sable Tier 1 Platforms.
2003
- 2006 Engineering
drawings were used to rigorously calculate and record the areas of the
structural elements (members and plates) for each platform. An assessment of the
severity and extent of damage sustained by area was performed from the
photographic evidence. All the above information was brought together in an
interactive database to enable negotiations to proceed. The
bottom line costs/durations and manpower requirements were derived using a
purpose built cost model. Nigeria
– damage to swamp facilities
2004
- present Following
willful damage to a number of oil/gas installations in the Niger Delta region,
Steve was engaged to perform the following activities:- · Engineering assessments – assessment of the status of the equipment items before and after the civil action and during on-going repairs. · Inclusion of information relating to the process and instrumentation systems. These
activities have involved the generation of a number of linked equipment
databases for each installation to aid in costing, inspection, condition
assessment and repair. Semi-submersible
drilling rig – thrusters repair
2003 Following
damage to a semi-submersible and claims for two sets of repairs and loss of hire
revenue, the scope was to identify the costs associated with the necessary
repairs, to the exclusion of costs associated with maintenance, betterment and
unnecessary support services. A
‘Negotiation Spreadsheet’ was developed to enable a flexible interpretation
of the information available and designed to allow the loss adjusters to examine
the options for apportioning the claimed costs during subsequent discussions
with the assured. Sable
– delayed start up claim
2005 Evaluation of the lost profits sustained by a Sable partner resulting from delayed start up of production. Cost models were developed to estimate the lost profits under a number of ‘start of production’ assumptions. HSE (UK Health and Safety Executive) - Monitoring of the structural response of the Spadeadam test rig to explosion loads. This project involved the design of the sensor system to measure high and low frequency structural response and the indirect measurement of vented gas velocities in the Phase 3b tests performed in September 1999. 1999 - 2000 HSE - The interpretation of Spadeadam test results. - Phase
1. Shell - Shearwater - Design of Temporary Refuge to withstand external blast loads 1998 - 1999 Shell - Shearwater - Independent Verifier for MechTool designed blast panels. 1998 - 1999 HSE - Blast capacity and response of tested panels using Bigg's method 1998 - 1999 Texaco - Captain - Blast response analyses 1999 Shell - SPOTS Compression module - Blast wall risk analysis 1999 HSE - Development of a method for the prioritisation of
research needs. 1998 HSE - Review of approaches to fire, blast and accidental loads 1997-1999 This project involved a review of codes including military, earthquake, Nuclear, Norwegian, and US codes in order to identify useful approaches for offshore application. JIP - Composites Topsides Study - Review of safety issues 1997-1999 Responsible for the definition and examination of fire and explosion scenarios relevant to the safety of novel topsides designs involving the extensive use of GRP. Various - Minimal facilities Platforms - Fire consequence analyses 1997-1999 Statoil - Siri accommodation module - Consequence review of jet fire impact 1998 Examination of the consequences ALARP load cases involving jet fire impingement on the TR for the Siri jackup platform HSE - Sensitivity of response of offshore structures to fire and blast 1995 - 1996 Project Manager of a major study of the sensitivity of response of structures to explosions, fires and combined fire and explosion scenarios. The Direct Probability Method was developed and used to develop response surfaces and calculate directly probabilities of failure and other reliability measures. These measures were used to rank the resistance variables in order of importance. Connemara FPSO - Motion loads and blast response 1997 HSE/SCI - Comparative study on blast panel response 1997 MacCulloch FPSO - Topsides blast resistance assessment 1997 HSE - Safety Case review (explosion loading, response and risk assessment) 1996 - 1997 FABIG (Fire and blast information group) - steering committee member 1995 - 2000 HSE - Spadeadam Explosion test rig Structural Assessment 1996 Shell Brent Refurbishment Programme - Blast relief louvres, testing and acceptance 1994 Marathon Ireland Kinsale Platforms - Blast pressures and blast consequence analysis 1994 Elf Enterprise Claymore - Dropped object study 1994 Agip UK Tiffany - Severe shock studies, explosions and ship impact 1992 B.P. Engineering - Blast and fire resistance studies 1991 - 1993 Forties - Blast resistance capacities 1991 Thistle - Fire loads and response, blast response 1992 - 1993 Buchan - Fire loads 1992 Clyde - Fire and blast response, response to projectiles 1993 Magnus - Fire response 1993 E.C. - Development and testing of a lightweight blast walling system 1991 - 1994 British Gas Allington - Fire and explosion consequences of gas release 1990 Shell - Prepared 'Explosion Protection - Project Specification’ - Brent 1990 Shell - Blast assessment of Brent 'D' cellar deck 1990 Amerada Hess Rob Roy - Blast screen projectile and blast load assessment 1990 BP Artificial Lift Consortium - Barrier wall design Forties 1990 J.I.P. Fires and Explosions - Response to blast and the use of alternative materials 1989 - 1992 Shell Brent 'C' and Spar - Blast wall and explosion relief review 1989
|
|
|